Procedure of issuing commissioning permits for capital construction objects

 

Administrative procedure (Further - procedure) The name of the document given as a result of the procedure (Further – resulting document) and its purpose. Name of the body or organization that issues the resulting document List of documents needed for the procedure Maximal term of the procedure Regulations and standards of the procedure
1 Issuing of conclusion by the government construction oversight authority (in case of construction of objects which project documentation is subject to state examination, or is a typical project documentation or is its modification, which received positive conclusion of examination) Opinion letter on the conformity of the built object of capital construction with requirements of technical regulations (rules), other legal acts and project documents, including the requirements for energy efficiency and requirements for equipping a capital construction object with devices for measuring energy resources used.
It is a prerequisite for obtaining a commissioning permit for a capital construction object
Inspectorate of State Construction Supervision under the Ministry of Construction, Architecture and Housing Policy of the Udmurt Republic 1. Notification about elimination of violations indicated in the acts on inspection results by the government construction oversight authority. 2. Notification about completion of construction works.

10 working days from the date of application

Town Planning Code of the Russian Federation (Articles 52, 54)
RF Government Resolution dated February 1, 2006 # 54 "On the State Construction Supervision in the Russian Federation"
2 Signing of the act on technological connection of a capital construction object to networks of electricity, heat, water supply, sewerage networks of gas supply (if the project provides connection to the networks) The act of technological connection of a capital construction object to networks, signed by the developer and the company operating the electricity network.
The document shows the performance by the developer and the company operating the networks, of contractual obligations on technological connection of a capital construction object to networks. The act of technological connection of a capital construction object to networks is necessary for making the contract and supply of resources to the object of capital construction
Organisation operating electrical supply networks Not determined Not determined RF Government Resolution as of December 27, 2004 # 861 "Rules of non-discriminatory access to power transmission services and provision of these services, rules of non-discriminatory access to services for supervisory control in electrical energy industry and provision of these services, rules of non-discriminatory access to services of a trading system administrator of the wholesale market and provision of these services and the rules of technological connection of power receivers of electric users, electric power generation facilities as well as power grid facilities belonging to grid operators and other persons, to electric networks" (paragraph 19).
RF Government Resolution dated February 13, 2006 # 83 "Rules for the definition and provision of technical conditions for connecting capital construction facilities to engineering networks, and Rules of connecting a capital construction object to engineering networks" (paragraph 10)
RF Government Resolution as of May 17, 2002 #317 "Rules for the use of gas and the provision of gas supply services in the Russian Federation"

(paragraph 28)

3 Investigation of conformity of energy efficiency rating of gas-powered equipment with passport or project parameters (if there is autonomous heating with a total calculated thermal capacity of gas-powered equipment more than 100 kW) The act of conformity of energy efficiency rating of or gas-powered equipment with passport or project parameters.
The document is required for making a contract of gas supply.
Federal Service for Ecological, Technological and Atomic Supervision

Rostekhnadzor

West-Ural Department


Notification

10 days from the date of receipt of notification from the developer by the Government Energy Agency of the constituent of the Russian Federation, the notice from the builder RF Government Resolution as of May 17, 2002 #317 "Rules for the use of gas and the provision of gas supply services in the Russian Federation" (paragraph 29)
4 Conclusion of the contract on the maintenance of gas equipment and emergency dispatch services (if the project provides connection to gas supply networks) Contract on technical maintenance of house gas equipment and emergency dispatch services.
The document is required for concluding a contract of gas supply.

Specialized organization having emergency dispatch service and permit to gas network services

Developer’s application

Not determined RF Government Resolution dated July 21, 2008 # 549 "On the procedure of gas supply for domestic needs of citizens" (paragraph 9)

5

Conclusion of a gas supply agreement with the company that provides gas supply The contract for the gas supply.
The agreement concluded with the developer organization operating gas network.
The document is required for the gas supply to the object of capital construction
Organisation operating gas network Documents confirming: 1) the size of the total area of residential and non-heated premises; 2) the number of persons living in dwellings;

3) the composition and type of gas-powered equipment;

4) the type of installed device (node) of gas;

5) a copy of the contract on technical maintenance of the house gas equipment and emergency dispatch services;

6) a copy of the act of determining the boundaries of the division of property

30 days from the date of the developer’s application


RF Government Resolution dated July 21, 2008 # 549 "On the procedure of gas supply for domestic needs of citizens"

(paragraphs 5-18)



6 Conclusion of a contract on electric supply Contract on electric supply concluded by the developer with the organization operating electricity networks.
The document is required for the delivery of electrical energy to a capital construction object of the developer.
Organization operating electricity networks Developer’s application on conclusion of a contract on electric supply 30 days from the date of the developer’s application RF Government Resolution as of December 27, 2004 # 861 "Rules for technological connection of power receivers of electric users, electric power generation facilities as well as power supply network facilities belonging to grid operators and other persons, to electric networks" (paragraphs 9-25)
7 Signing of the act on preparedness of on-site and internal networks and equipment of a capital construction object to be connected to the gas network, heating, water supply and sanitation. The act of preparedness of on-site and internal networks and equipment of a capital construction object to be connected to the network, is signed by the developer and the company operating the gas transmission networks
A document showing implementation of connection conditions by the developer, the presence of crimped seals, preparedness of on-site networks to the receipt of resources
The act of preparedness of on-site and internal networks and equipment of a capital construction object to be connected to the network is necessary for concluding a contract of gas supply
Organisation operating gas networks Notification by the developer of the organization operating gas networks about the preparedness of on-site and internal networks and equipment of a capital construction object to the reception of resources The term is established by the contract on connection of a capital construction object to gas supply networks RF Government Resolution dated June 9, 2007 # 360 "Rules for the conclusion and execution of public contracts on connection to the systems of communal infrastructure" (paragraph 20)
8 Receipt of a release to service devices and objects created for the accession to the heating system

The act of a release to service devices and objects created for the accession to the heating system.
A document certifying conformity of heat supply devices with the established requirements
The act of a release to service devices and objects is necessary for the conclusion of the contract of heat supply
Federal Service for Ecological, Technological and Atomic Supervision Rostekhnadzor West-Ural Department

Not determined

Not determined RF Government Resolution dated February 13, 2006 # 83 "Rules for the definition and provision of technical conditions for connecting capital construction facilities to engineering networks, and Rules of connecting a capital construction object to engineering networks" (paragraph 23)
9 Conclusion of contract on heat supply and act on balance participation separation and operational responsibility Contract on heat supply, concluded by developer and company, operating heat supply networks.
Contract provides the supply of heat energy to the object of capital construction.
Organization, operating heat supply networks Offer (claim) of developer 30 days since the organization, operating heat supply networks receives the offer from the developer Housing Code of Russian Federation (article 153)
Order of Government of Russian Federation from 14.02.2012 N 124 "Rules, obligatory during the conclusion of contracts of utility resources supply for the purpose of utility services rendering" (p. 3 - 6)
10 Signing of the act on washing-off of water supply devices and facilities necessary to connect to the water supply system The act on washing-off of water supply devices and facilities. The document confirming disinfection of intrahouse water supply systems.
The act is needed for signing the water supply contract
Developer Not determined Not determined RF Government Resolution dated February 13, 2006 # 83 "Rules for the definition and provision of technical conditions for connecting capital construction facilities to engineering networks, and Rules of connecting a capital construction object to engineering networks" (paragraphs 19, 20)
11 Signing the contract of water supply, sanitation The contract on water supply concluded with the developer and the organization operating water supply and sewerage systems.
The contract covers supply and drainage of a capital construction object
Organization operating water supply and sewerage systems Developer’s offer (application) 30 days from receipt of the offer (application) from the developer by the organization operating water supply and sewerage systems Housing Code of the Russian Federation (Article 153)
RF Government Resolution as of February 14, 2012 # 124 "The rules required for the conclusion of contracts on public utilities supply with the aim of provision of public services" (paragraphs 3 - 6)
12 Preparation of technical plan of capital construction object Technical plan.
Technical plan is the document, containing certain data, entered into the state estate cadaster, and data on building, facility, premises or object of unfinished construction, necessary to register such object, or data on part or parts of such estate object, or new ones necessary for entering into the state estate cadaster, data on such object to which the cadaster number is assigned.
Federal service of state registration, cadaster and cartography -cadastral extract for the land property the object is located on; -project documentation of technical passport for the object, built no later than 01.01.2013; -object building permit;

-reference or local self-government body act оn postal address assignment (for newly created objects);

-other documents that cadaster engineer may need in order to execute cadaster works.


10 working days

Order of Ministry of economic development of Russian Federation from 23.11.2011 N 693 "On approval of facility technical plan mode and preparation requirements" (with alterations and amendments)
Federal law from 24.07.2007 N 221-ФЗ "On state cadaster of property"
13 Issue of a permit for putting the object into operation Permit for putting the object into operation
Certifies the execution of construction works in full in accordance with the building permit, compliance of the built object of capital construction with the land plot development plan and project documentation
It is the basis for state carrying out State cadastral registration of non-movable assets and for state registration of rights for non-movable assets

Main Department of Architecture and Urban Planning of Izhevsk City Administration, the Ministry of Culture and Tourism of the Udmurt Republic, the Ministry of Construction, Architecture and Housing Policy of the Udmurt Republic



1) The application for a permit for putting the object into operation;

2) land title documents (only required if these documents (or copies or the information contained) are missing in the Unified State Register of rights to immovable property and transactions with it);

3) the development plan of the land or in the case of the construction of the linear object, the area planning design and the boundary-setting plan - is not required since July 1, 2012;

4) construction permit - not required since July 1, 2012;

5) the act of acceptance of the object of capital construction (in the case of carrying out construction under the contract) - is required since July 1, 2012 if the document (a copy, or the information contained in it) is not at the disposal of state authorities, local authorities or organisations which fall within the jurisdiction of state authorities or local government bodies;

6) a document confirming compliance of the built object of capital construction with the requirements of technical regulations and signed by the person performing the work - is required since July 1, 2012 if the document (a copy, or the information contained in it) is not at the disposal of state authorities, local authorities or organisations which fall within the jurisdiction of state authorities or local government bodies;

7) a document certifying the conformity of the built object of capital construction with project documents, including the requirements of energy efficiency and the requirements of equipping of objects of capital construction with devices for measuring energy resources used, and signed by the person carrying out construction works (a person engaged in the construction, and the developer or technical customer in the case the construction is carried out on the basis of the contract, as well as the person exercising the building control, in the case of the construction supervision on the basis of the contract) - is required since July 1, 2012 if the document (a copy, or the information contained in it) is not at the disposal of state authorities, local authorities or organisations which fall within the jurisdiction of state authorities or local government bodies;

8) documents confirming compliance of the built object of capital construction with technical specifications and signed by representatives of organizations engaged in engineering network operations (if any) - is required since July 1, 2012 if these documents (copies or information contained in them) are not at the disposal of state authorities, local authorities or organisations which fall within the jurisdiction of state authorities or local government bodies;

9) a scheme showing the location of the built object of capital construction, the location of networks of engineering and technical support in the boundaries of the land plot and a land plot layout and signed by the person carrying out construction works (a person engaged in the construction, and the developer or technical customer in case the construction, reconstruction is carried out on the base of the contract), except for the cases of construction, reconstruction of the linear object - is required since July 1, 2012 if these documents (copies or information contained in them) are not at the disposal of state authorities, local authorities or organisations which fall within the jurisdiction of state authorities or local government bodies;

10) the conclusion of the government construction oversight authority on compliance of the built object of capital construction with requirements of technical regulations and project documentation, including the requirements of energy efficiency as well as the requirements of equipping of the capital construction object with devices for measuring energy resources used - is not required since July 1, 2012.

11) a document confirming the conclusion of the contract of obligatory insurance of civil liability of the owner of a dangerous object for injury in an accident at the hazardous facility in accordance with Russian legislation on compulsory insurance of civil liability of the owner of a dangerous object for injury in an accident on a dangerous object;

12) the act of acceptance of work performed on the preservation of a cultural heritage object, approved by the relevant body of cultural heritage protection by the Federal Law as of June 25, 2002 # 73-FZ "On objects of cultural heritage (historical and cultural monuments) of peoples of the Russian Federation", during restoration, preservation, renovation works of the facility and its adaptation for modern use.

13) Technical plan prepared in accordance with the requirements of Article 41 of the Federal Law “On the State Cadastre of Immovable Property”.


The Government of the Russian Federation may establish other documents required to obtain permission to put the object into operation, in order to obtain the full information necessary for the public registration of a capital construction object.

10 days

Town Planning Code of the Russian Federation (Article 55)


RF Government Resolution dated November 24, 2005 # 698

"On the form of the building permit and the form of permit to put the object into operation"


Administrative regulation on delivering of municipal services "Preparing and issuing permits to put capital construction projects into operation" (amended by the Decree of Izhevsk City Administration as of 16.12.2013 #1541 / 6)


The Order of the Ministry of Regional Development of the Russian Federation of July 2, 2009 # 251 "On the organization of work of issuing building permits and permits for commissioning of capital construction projects, referred to in part 5.1 of Article 6 of the Town Planning Code of the Russian Federation, which are located on land plots not subject to town-planning regulations or for which town-planning regulations are not determined, with the exception of those capital construction objects, for which carrying out the state examination of project documentation and (or) building permits are assigned to other federal bodies of executive power "


Federal Law of July 1, 2011 #169-FZ

"On Amending Certain Legislative Acts of the Russian Federation" (Article 74)